M2/M3 BFV: TROUBLESHOOTING - OD1610 - LESSON 2/TASK 1
252-10-2. Once the launcher has been stowed, he powers down the turret and
places the MASTER POWER switch to the OFF position. The last step in this
box directs him to perform STE-M1/FVS test number 2640. The procedures for
performing this test can be found on page 3-249 of the TM.
FIGURE 18.
PALM SWITCHES.
Before beginning the actual test procedures, SGT Stryker reads through the
Initial Setup section to see if any additional tools, equipment, personnel
or references will be required. For this procedure the only new items that
SGT Stryker will require is the STE-M1/FVS test set and TM 9-4910-751-14-1.
After gathering together these additional pieces of equipment, SGT Stryker
connects the STE-M1/FVS to the vehicle distribution box. When the test set
is connected, he performs the self-test. Finding no faults with the self-
test, SGT Stryker follows the no arrow to the next box of instructions where
he
84