M2/M3 BFV: HULL POWER DIST SYSTEM - OD1606 - LESSON 2/TASK 2
procedures outlined in TM 9-2350-252-20-2-2, page 4-2.
Once the
turret step floor plate is removed, SGT Haskell manually traverses
the turret to 2300 mils. After the turret has been traversed to 2300
mils, SGT Haskell removes plug 1W4P1 (1) (figure 41) from jack 2A7J2
(2).
Once the plug has been removed, SGT Haskell once again moves
the MASTER POWER switch to the ON position and measures the voltage
between pin B (3) of plug 1W4P1 and ground.
To make this
measurement, SGT Haskell uses the TS-352B/U multimeter that was
discussed in paragraph 3b, on page 47 of lesson 2, task 1.
FIGURE 41.
REMOVING PLUG 1W4P1 FROM
JACK 2A7J2.
59